Redmond Ridge Roundabout Project details
Project Timeline
Work hours
Lane restrictions through the intersection – Only during work hours
Full 14-day intersection closure (all vehicles except emergency response)
The purpose of the closure is to build the roundabout lanes from the ground up. Crews will build the subgrade and pour several layers of asphalt and concrete. Exact dates are to be determined; however, the closure is expected to begin in middle or late October and last through late October or early November.
Why the project could not be completed in summer 2023:
King County made a sincere effort to initiate work on the roundabout project in early spring 2023. Our initial plan was to schedule the full intersection closure for June or early July when school was out of session. Despite our dedicated efforts, we unexpectedly encountered challenges during both the project review and approval process and in securing a contractor for the project. Consequently, actual start of construction was postponed until late summer 2023. Additionally, it is important to note that postponing construction until the summer of 2024 is not feasible due to funding constraints. We understand the inconvenience this may cause, especially when it comes to transportation to and from Timberline Middle School and neighboring schools. Our Road Services team is actively collaborating with the project contractor to complete the project as swiftly as possible.